Big-tech buyers have announced 7,754 MW of nuclear capacity across six named deals between September 2024 and January 2026: Meta leads with 4,499 MW (Vistra, Oklo, TerraPower), Amazon 1,920 MW (Talen/Susquehanna), Microsoft 835 MW (Constellation's Three Mile Island Unit 1 restart, targeted 2027), Google 500 MW (Kairos, with TVA). Of the total, 2,390 MW is small or advanced reactors (Oklo, TerraPower, Kairos) — the newest reactor designs' first anchor customers are AI companies. No new deal has been announced since January 2026.
| deal | mw | announced | notes |
|---|---|---|---|
| Microsoft / Constellation (Crane, TMI U1) | 835 | 2024-09 | restart targeted 2027 |
| Amazon / Talen (Susquehanna) | 1920 | 2025-06 | through 2042; full volume by 2032 |
| Google / Kairos (with TVA) | 500 | 2025-08 | 500 MW by 2035; Hermes 2 ~50 MW ops 2030 |
| Meta / Vistra | 2609 | 2026-01 | 2,176 MW operating plants + 433 MW uprates, 20-yr PPAs |
| Meta / Oklo (Ohio campus) | 1200 | 2026-01 | first phase as early as 2030 |
| Meta / TerraPower | 690 | 2026-01 | delivery as early as 2032 |
Download: CSV · JSON — compiled data CC BY 4.0; underlying sources keep their own terms.
Announced capacity from SEC filings and company releases — not operating megawatts: the earliest delivery is the Crane restart targeted for 2027, and several deals run to 2030–2035. Deal MW types differ (PPAs on operating plants vs new construction). "None since January 2026" describes this log of named deals, not a claim about private negotiations.